An innovative system for installing power cables – the WATUCAB method

As part of the implementation of the project entitled “Design and construction of a 110kV cable line from GPZ Kamień Pomorski – RS Rybice – GPZ Skrobotowo together with the RS Rybice network switching station and the expansion of GPZ Skrobotowo for the purpose of evacuating power from WF Rybice, FW Starza and WF Karnice II with a total power of 88MW” WATUCAB technology was used , which is an innovative method of installing medium and high voltage power cables using cable pipelines. It is a technology that combines the benefits of hydraulic pushing and blowing of power cables.